Thredbo Resort | 500 tonnes | Completed 2026
Asphalt mill and fill across roads and carparks at Thredbo Resort, on a three-week program with public access maintained throughout.
Like Perisher, this was a job where the weather set the sequence of works rather than the other way around, and where a lost day could not be allowed to become a lost week. Plant was positioned and haulage timed so that every workable shift was used.
Around 500 tonnes placed, with profiling, base compaction, proof roll, bituminous spraying, asphalt placement, compaction and testing all delivered by our own crew.
Related Projects

HAVE A PROJECT TO PRICE?
Send us:
Project location
Scope / drawings
Approximate quantities
Required timeframe
Tender closing date

Everything procurement needs, in one PDF
Company details and ABN, certifications, key personnel, plant and project record. Download the capability statement, or ask us for certificates and insurances directly.
Download capability statement
bottom of page